新步定向定价商品房项目同样在紧锣密鼓推进中。

施工现场塔吊林立、机械轰鸣、车辆穿梭。该项目总投资超17亿元,用地面积约134亩,总建筑面积约31.5万平方米,规划建设住宅、幼儿园及公共配套服务用房。
目前,项目正处于紧张的桩基施工阶段,碎石桩施工已全部完成,方桩施工进度已达80%,灌注桩施工稳步推进中。按照计划,项目将于第三季度进入主体结构施工阶段,第四季度部分楼栋有望实现封顶。
当前正值项目建设的黄金期,鲤城将咬定目标、攻坚克难,持续强化要素保障、紧盯项目进度、压紧压实责任,全力推动重点项目落地见效,为高质量发展打下坚实基础、提供有力支撑。
来源:鲤城新闻网