作为西部陆海新通道骨干工程,平陆运河的建设进度始终备受瞩目。5月1日,平陆运河青年枢纽下游2号围堰正式破除,河水缓慢有序注入青年枢纽船闸,标志着该枢纽工程正式进入有水调试阶段,也意味着平陆运河马道、企石、青年三大枢纽建设全面迈入冲刺关键期,向通航目标迈出坚实一步。

“为加快开辟广西及西南地区通往东盟运距最短、最经济、最便捷的水运大通道,助力构建国内国际双循环新发展格局,‘五一’假期,平陆运河13000名建设者坚守岗位,全力冲刺今年9月通航试运行目标。”平陆运河集团相关负责人介绍,截至目前,平陆运河整体工程量已完成超94%,“一河贯通,八桂向海”的梦想蓝图正加速从规划变为现实。
Xin Fangdoushan Tunnel, a Controlling Project on the Entire Yifu High-Speed Railway Line, Is Under Round-the-Clock Uninterrupted Construction
下一篇Pile Foundation Construction of Chishui River Grand Bridge Reaches 90% Completion

2026-09-28 1157 0

2026-09-24 10586 0

2026-09-23 10714 0

2026-09-22 10808 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)