Nearly 90% of Pile Foundation Construction Completed for Section A1 of Baiqi Channel Project

2026-03-10 3663 0人评论

More than half of the overall construction of structures for the Baiqi Channel Project has been completed, with land and sea construction advancing in parallel and progressing at multiple points.




A total of 449 personnel (including construction workers) have returned to their posts after the holiday, 73 machines are on site, and 15 work points have resumed construction.


At present, all trestle bridges have been fully erected, and the main structure and roadbed works are being advanced simultaneously.


Among them, pile foundation construction in Section A1 is nearly 90% complete, while pile caps, pier columns, and the main tower are progressing on schedule. In Section A2, the retaining piles and main trestle bridge have been completed, the lowering of steel pipes for water-based pile foundations is nearing completion, pile foundation construction has exceeded 90%, and ancillary works such as roadbed, pipe networks, and retaining walls are being carried out in parallel.


Source: Quanzhou SASAC

评论 (0)

TOP