Zhongyan Dadi Wins 93.2479 Million Yuan Bid for Pile Foundation Construction of 31URA Cooling Tower in Phase I of Jiangsu Xuwei Nuclear Heating and Power Plant

2026-01-30 6182 0人评论

       On January 29, Zhongyan Dadi announced that the company recently received the "Notice of Award" issued by China Energy Engineering Northwest Urban Construction Co., Ltd., confirming the company as the winning bidder for the pile foundation engineering section of the Jiangsu Xuwei Project of the Nuclear Power Branch. The project is named the Construction and Installation Project of Natural Draft Cooling Towers for Units 1, 2, and 3 of Phase I of the Jiangsu Xuwei Nuclear Heating and Power Plant (Section II)—31URA Cooling Tower Pile Foundation Construction Project, with a winning bid amount (including tax) of 93.2479 million yuan.

评论 (0)