(b)钻机设计:因钻孔直径大,回转扭矩大,故要求钻头结构简单、质最轻、钻进阻力小、排渣顺畅、使用方便。
(c)钻孔方法:为确保钻孔顺利进行,一般采用分级扩孔,反循环排渣,钻进中经常调整泥浆性能。
(d)钻进参数:转速8r/min;钻压30kN (正循环钻进),25kN (反循环钻进)泵量2X108m3/h (正循环钻进),180m3/h (反循环钻进)。
(e)泥浆性能及配方,对泥浆性能的要求:含砂量<4% ;黏度18~20s;密度1.05~1.20kg/L; pH值8~9。上部淤泥层含有大量有机质,对泥浆的破坏力强,且钻孔泥渣多,因此需配制抗破坏力强和具浮渣能力的泥浆。用CMC低固相泥浆,其配比为:黏土(膨润土):水:纯碱: CMC=1 : 5. 59 : 0. 03 : 0.02o
Major Equipment Manufacturing Projects with Total Investment of 12.9 Billion Yuan Settle in Jiangning Binjiang
下一篇Assembly and Connection of Hollow Piles

2024-09-29 13335 0

2024-09-20 13336 0

2024-09-20 13180 0

2024-09-19 12457 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)