The Ningbo Century Avenue (Xingning Road–Dongming Road) utility tunnel project, constructed by Hongrun Construction Group Co., Ltd. and jacked by Guangzhou Jintu Geotechnical Engineering Technology Co., Ltd., has been successfully completed.

On-site photo of the pipe jacking breakthrough
The project is located in Yinzhou District, Ningbo, and was constructed using the pipe jacking method. It launched from the No. 6 Fuming Substation, crossed Century Avenue westward, and reached the receiving shaft on the west side of Fuming Substation. The project used a large-section pipe jacking with a cross-sectional dimension of 9.1 m × 4.4 m, a total jacking length of 92.5 meters, a designed longitudinal slope of 2.3%, and a cover depth of 12.03–14.45 meters.
The pipe jacking construction area has a complex environment, with main characteristics including: 1) busy surface traffic, with heavy vehicle flow on Century Avenue; 2) dense underground pipelines, requiring crossing of multiple municipal pipelines such as rainwater, communications, and water supply; 3) numerous surrounding buildings, including residential houses, the substation, and important structures such as the existing utility tunnel. These factors brought considerable technical difficulty and safety risks to the pipe jacking construction. In addition, the strata crossed by the pipe jacking are mainly mucky silty clay and silty sand, with typical soft-soil stratum characteristics. Such strata are extremely sensitive to construction disturbance, further increasing the difficulty and safety risks of jacking construction.

Plan view of the pipe jacking project
Project characteristics and countermeasures 1 Construction risks of large-section pipe jacking:The 9.1 m × 4.4 m large-section pipe jacking is prone to machine pitching and torsion, and in mucky soft-soil strata the construction risks increase sharply. Through end reinforcement, as well as measures such as strengthened attitude monitoring during jacking and auxiliary lifting by thick mud pressure via correction jacks, the pitching and attitude torsion of the pipe jacking machine were effectively controlled. 2 Pressure of traffic and pipeline protection:The pipe jacking construction not only passes beneath the busy main road of Century Avenue but also beneath multiple pipelines such as rainwater and communications. The crossing range consists mainly of mucky silty clay and silty sand strata, and the highly disturbance-sensitive geological conditions increased the difficulty of controlling ground deformation and protecting pipelines. During pipe jacking construction, through reasonable muck conditioning, strict control of the balance between excavation volume and muck discharge at the face, and reasonable control of the faceearth pressure, stable pressure-retaining muck discharge was achieved. At the same time, patented technology was used to inject composite thick colloidal mud in front of the machine head, around the machine body and around the pipe segments to squeeze and fill ground loss, reducing stratum deformation and construction disturbance. Throughout the process, monitoring of the road surface and pipelines was strengthened and intensified at a frequency of 3 times per day, and monitoring data were promptly fed back to the operators to guide the jacking construction. Through the above measures, the safety of road traffic and pipelines was ultimately effectively ensured. 3 Construction risks in unfavorable strata:The pipe jacking crosses mucky soil and silty sand layers, typical soft-soil geology. These strata are particularly sensitive to construction disturbance, especially the silty sand layer, which has a loose structure and poor self-stability and is prone to quicksand under hydrodynamic action, aggravating soil and water loss and causing ground settlement or heave, and is also prone to screw conveyor gushing. During construction, by strengthening muck conditioning measures and optimizing the ratio of conditioning agents, the workability of the muck was well improved and screw conveyor gushing was effectively avoided. By closely monitoring groundwater levels, quicksand and seepage failure were prevented; by optimizing jacking construction parameters, strengthening grouting technology, and real-time monitoring and other measures, the impact of stratum disturbance sensitivity was minimized to the greatest extent, making ground deformation controllable. 4 The launching shaft structure for pipe jacking is complex, and construction faced three main difficulties:First, the existing reaction wall was only a 300 mm thick partition wall, and the distance from the main structure of the shaft wall reached 2.2 meters, so the jacking reaction force could not be effectively transmitted to the main structure; second, there was a large height difference between the shaft bottom slab and the outer bottom surface of the pipe jacking passage, so the pipe jacking machine could not directly jack along the guide rails on the launching shaft bottom; third, the already constructed shear walls and floor slabs were numerous, resulting in narrow working space and difficult equipment lifting and installation. In response to the above difficulties, measures such as adding a temporary reaction structure between the partition wall and the main structure, erecting a 5-meter-high temporary launching steel platform, and optimizing lifting equipment effectively solved the problems. 5 Efficiency constraints of the three-cell utility tunnel:The pipe-jacked utility tunnel was designed in a three-cell form, and no partition wall was provided in the middle during precasting of the pipe segments. Because of the large span of the pipe segments and the lack of mid-span support, insufficient load-bearing capacity at the pipe crown was found during pipe jacking construction, so two rows of steel supports were added inside the pipe. However, this operation compressed the pipe jacking working space by 40% and reduced muck discharge efficiency. During construction, the problem was effectively solved by optimizing the size of the muck cars and increasing their number. In response to the characteristics, key difficulties, and risk points of this project, our company strictly followed the design drawings and relevant specification requirements, and exercised strict control over each technical step through meticulous construction organization and scientific management. During construction, we carried forward the craftsman spirit, overcame numerous difficulties, and ultimately completed this utility tunnel pipe jacking task with high quality and high efficiency. Guangzhou Jintu has always adhered to the business philosophy and value orientation of "integrity, pragmatism, innovation, and development." Among these, integrity is the cornerstone of the enterprise, pragmatism is the spirit upheld by the team, innovation is the driving force for sustainable development, and development is the eternal absolute truth. Guided by these core concepts, Jintu people have given full play to their intelligence and talent, cut through obstacles in fierce market competition, and continuously driven the company to develop into a benchmark enterprise and industry leader in the field of urban underground space and underground engineering construction in China.





Product Recommendation | Tysim KR110D Power Grid Dedicated Drilling Rig for Power Construction
下一篇"First Mao Yisheng Youth Science and Technology Academic Forum" Selected as One of the "Top Ten Most Influential Academic Conferences" by the Beijing Association for Science and Technology

2026-09-28 1137 0

2026-09-24 10491 0

2026-09-23 10629 0

2026-09-22 10708 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)