At the busy construction site of a large non-ferrous polysilicon project in Northwest China, the segmented lifting of a 352-ton, 64-meter-tall distillation column became the core battle for accelerating the project.

The lifting site is the battlefield!
A XCMG XGC16000 (1,250-ton class) crawler crane serves as the main crane, unleashing tremendous power and outstanding stability in the super-lift main boom configuration, fully demonstrating the prowess of a "major-country heavy equipment"; the high-performance XGC450 (450-ton class) crawler crane works flexibly in coordination, providing precise assistance.
On site, the upper and lower column sections weighing 127 tons and 225 tons were steadily hoisted. Under millimeter-level precision control, the hook acts like a precise "mechanical hand," displaying extraordinary skill in handling massive loads with ease.

Two machines in tandem, winning with precision!
The two XCMG "steel giants" worked in seamless coordination, ensuring the entire lifting process was safe, efficient, and smoothly connected.
As the final column section was precisely aligned at the predetermined height, this highly difficult distillation column lifting task was successfully completed! This not only marks the successful installation of the project's key core equipment, but also represents a solid step forward for the large non-ferrous polysilicon industrial upgrading project in Northwest China.

From the precise lifting of thousand-ton heavy columns to engineering project support under the "Belt and Road" initiative, XCMG lifting machinery, with outstanding performance and reliable quality, serves global infrastructure construction and writes new possibilities in major engineering projects worldwide.
North股份 Company Holds 2025 "Work Safety Month" Launch Ceremony and "Safety Commitment Pledge" Signing Ceremony
下一篇Zoomlion: Rapid Response for the 'Three Summer' Battle, Craftsmanship and Skill Ensure Granaries Are Full

2026-09-28 1137 0

2026-09-24 10491 0

2026-09-23 10629 0

2026-09-22 10708 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)