CABR Foundation | "Prestressed" Technology Takes the Stage: Foundation Pit Support Without Tiebacks or Struts — Prestressed Concrete Cantilever Pile Foundation Pit Support Technology

2025-06-03 4502 0人评论

Prestressed Concrete Cantilever Pile Foundation Pit Support Technology



Technology Introduction 

The surrounding environment of newly built underground spaces is becoming increasingly complex, and foundation pit excavation is often affected by existing buildings, municipal infrastructure, andproperty line boundaries. For complex surrounding environments, conventional support methods each have their own limitations. To address these issues, CABR Foundation Engineering has developed a new type of prestressed concrete cantilever pile support structure that can limit the displacement of the support structure.

Horizontal Description

The prestressed concrete cantilever pile support structure does not require internal bracing that would interfere with earthwork excavation and structural construction, nor does it requireanchor rodsthat would affect the surrounding environment of the foundation pit or encroach on space beyond the property line. Instead, steel strands are embedded in the support structure and prestress is applied to them in stages, creating a deformation tendency toward the outside of the foundation pit. After excavation, thehorizontal displacementof the support structure can be controlled within the allowable range, and the bending and shear capacity of the pile body is greatly improved. Compared with ordinary cantilever structures, the support depth is significantly increased. With the prestressed concrete cantilever support structure, the foundation pit earthwork can be excavated directly to the pit bottom without affecting the construction of the main structure. Compared with pile-anchor and internal bracing schemes, it can save construction time and has a lower overall cost.

The prestressed concrete cantilever pile support structure can be used for foundation pit support projects in situations where anchor rods cannot be installed, the schedule is tight, the area is large, or construction space within the property line is limited. It is especially suitable for strata that can provide a good embedment effect.

Demonstration Role 

This technology has been successfully applied in multiple projects, including Kunming Dianchi Pearl · Chenggong Wanda Plaza, Beijing Wuzhou Women's and Children's Hospital, Kunming Jintai International, Xi'an North Railway Station, and Fuzhou Xinnuo Communications R&D Building, achieving good economic and social benefits.


评论 (0)