In August and September 2021, affected by heavy rainfall, a landslide occurred behind the community, producing new deformation and damage. Through deformation monitoring, as of October 17, 2021, the horizontal displacements at two monitoring points in the middle-rear part of the landslide were 2,592 mm and 2,420 mm respectively; at the front edge, the three monitoring points on the constructedanti-slide pileshad total displacements of 672.673 mm (west), 424.511 mm (center), and 232.778 mm (east) respectively, and no obvious tilting or pile fracture of the anti-slide piles was found; within the community site at the front edge of the landslide, the displacements at two displacement monitoring points were 251 mm and 104 mm respectively.

(1) Multiple vertical slopes exist in the front edge area of the landslide, formingstress concentration phenomenaunder the thrust of the landslide, which greatly affects the building foundation and causes settlement and tilting of the building;
(2) The landslide area has abundant atmospheric precipitation. In seasons with sufficient rainfall, atmospheric precipitation infiltrates into the slope body and converts into groundwater. Becausesurface water seepage causes softening of the foundation soil, uneven settlement of the foundation occurs.
① Technical principle:By embedding anchor rods in the foundation to fix the pile-pressing frame and using the building's own weight as the reaction force, precast piles are pressed into the foundation in sections, and the pile bodies share the upper loads to improve the bearing capacity of the foundation.
· Requires extensive excavation and replacement materials, with a large workload and a long construction period
· Only applicable to shallow soft soil layers (treatment depth usually ≤3 m)
· Poor applicability to sites with deep soft foundations or high groundwater levels
Traditional reinforcement and rectification is often accompanied by high-cost pain points such as relocation and resettlement and construction disturbance to residents. Today, the "non-disturbance rectification" solution, led bynon-destructive controllable soil solidification technology, is redefining the safety governance standards for building foundation settlement.
Non-destructive controllable soil solidification technologyusesnew special composite materialsinjected into the foundation throughmicro-hole technology. The composite materials can penetrate and fill the voids in the soil body and rapidly consolidate with the soil, enhancing the density and stiffness of the soil body and forming a high-strength composite foundation. As the soil pressure increases and density rises, an upward jacking force is formed, lifting the residential building and thereby correcting the tilt.

In this project, the client highly recognized our company's technical strength based on the actual reinforcement and rectification results,commenting"Hengxiang Hongye's new technology saved 50% of the time compared with traditional rectification methods; the entire construction process involved no excavation and no noise, with zero disturbance to the living environment, and the construction cost for this building was reduced by 60%. It is both cost-saving and efficient, requires no moving of furniture, and is safe and environmentally friendly. It is a truly reliable technology that benefits the people!"
Company News | Multiple TRD Machines from Jing'an Heavy Industry Deployed to Build an Underground Barrier for Erwangzhuang Reservoir in Tianjin!
下一篇Zoomlion Expands Thailand Network with Tenth Branch in Ubon Ratchathani

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)