On November 30, as the blades of the F23 and F24 "wind turbines" began turning one after another, the first batch of wind turbines at the Yanshaping Wind Farm of the Guangxi New Energy Project were successfully connected to the grid and put into operation, marking a new stage in the project's construction and laying a solid foundation for full-capacity commissioning.
The Yanshaping work area of the Guangxi New Energy Wind Power Project is located in Lingtian Town, Lingchuan County, with an approved installed capacity of 120 MW and 20 wind turbine generator sets. The designed annual equivalent full-load utilization hours are 2,147.8 hours, and the designed average annual power generation is 257.736 million kWh.
Before the wind turbines were connected to the grid for power generation, the project department coordinated and allocated resources to avoid overlapping civil construction and equipment installation, further improving construction efficiency. At the same time, the project department continued to strengthen safety production management and conducted comprehensive hazard inspections of the commissioned units and collector lines. Two days after the back-feed power transmission of the booster station was completed, the first batch of wind turbines was successfully connected to the grid for power generation.
At present, the project has completed foundation pouring for 9 wind turbines and hoisting of 6 wind turbine generator sets; 21 kilometers of collector line cable laying has been completed, laying the groundwork for the subsequent commissioning and operation of the units. The project department will maintain its momentum, keep up the effort, and work tirelessly to successfully complete the annual targets and tasks.

Yanshaping Wind Farm
Henan Jiaozuo: Intelligent Tension Stringing Method Helps Complete the Jinshan-Xinxiang Expressway Crossing Project Successfully
下一篇PowerChina Makes a Splendid Appearance at the 18th China Engineering Technology Exhibition and the China-Africa Economic and Trade Expo

2026-09-28 1157 0

2026-09-24 10586 0

2026-09-23 10714 0

2026-09-22 10808 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)