First Batch of Wind Turbines at Yanshaping Wind Farm of Guangxi New Energy Project Connected to Grid and Put into Operation

2024-12-03 1947 0人评论

On November 30, as the blades of the F23 and F24 "wind turbines" began turning one after another, the first batch of wind turbines at the Yanshaping Wind Farm of the Guangxi New Energy Project were successfully connected to the grid and put into operation, marking a new stage in the project's construction and laying a solid foundation for full-capacity commissioning.

The Yanshaping work area of the Guangxi New Energy Wind Power Project is located in Lingtian Town, Lingchuan County, with an approved installed capacity of 120 MW and 20 wind turbine generator sets. The designed annual equivalent full-load utilization hours are 2,147.8 hours, and the designed average annual power generation is 257.736 million kWh.

Before the wind turbines were connected to the grid for power generation, the project department coordinated and allocated resources to avoid overlapping civil construction and equipment installation, further improving construction efficiency. At the same time, the project department continued to strengthen safety production management and conducted comprehensive hazard inspections of the commissioned units and collector lines. Two days after the back-feed power transmission of the booster station was completed, the first batch of wind turbines was successfully connected to the grid for power generation.

At present, the project has completed foundation pouring for 9 wind turbines and hoisting of 6 wind turbine generator sets; 21 kilometers of collector line cable laying has been completed, laying the groundwork for the subsequent commissioning and operation of the units. The project department will maintain its momentum, keep up the effort, and work tirelessly to successfully complete the annual targets and tasks.

Yanshaping Wind Farm


评论 (0)

TOP