Recently, at the construction site of the Shandong Linzi to Linyi Expressway (hereinafter referred to as the "Linlin Expressway"), workers were installing the central median guardrail. The completed road is smooth and broad, stretching into the distance, and the construction of the Linlin Expressway has entered the final sprint stage toward full-line opening to traffic.

The Linlin Expressway connects nine counties and districts across the two cities of Zibo and Linyi. It links to the Zhanlin Expressway in the north and reaches the Rilan Expressway in the south, crossing the Qingyin, Jiwei, Qinglan, and Rilan expressways, and intersecting with the Dongliang Expressway under construction and the Weizou Expressway soon to be built, achieving interconnection among six expressways. The main line of the project has a total length of 192.618 kilometers, of which the remaining section from Zhongzhuang Interchange to Yimeng Hub is expected to be completed and opened to traffic this month, at which point the Linlin Expressway project will achieve full-line connectivity.
The Linlin Expressway is the project under construction in Shandong Province with the longest total tunnel mileage (45 kilometers of single-tube length), the largest number of tunnels (15), and the most complete range of rock types, and can be called the "Shandong Highway Tunnel Museum".
Over 2,000 Workers Stay on the Front Line to Ensure the Timely Breakthrough of the Changlinggang Tunnel on the Chongqing-Wanzhou High-Speed Railway
下一篇Right-line Shield Tunnel from Luomashi Station to Huo-Luo Intermediate Ventilation Shaft on Phase III of Chengdu Rail Transit Line 18 Successfully Breaks Through

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)