Zhuanglang Goes All Out to Accelerate Project Construction on a New Track

2024-09-26 2025 0人评论

In recent years, Zhuanglang County has firmly established the orientation of "development as the priority, projects as the focus, and practical work as the foremost," adhered to the concept of "projects as the king," focused on advantageous industries, concentrated efforts on "investing" in projects, focused on people's livelihood to "build" projects, and optimized the environment to "attract" projects, consolidating the cornerstone of high-quality development with the effectiveness of high-quality project construction and solidifying the "ballast stone" of economic development.

As of now, Zhuanglang County has implemented 8 key projects in 2024, with an investment of 241 million yuan completed that year. At the construction sites of various key projects, the vast number of builders are racing against time to seize the construction period and grasp progress. Project construction is in full swing, and the "construction drawings" are gradually turning into "realistic paintings." The Zhuanglang County Small and Medium-sized Enterprise Entrepreneurship Incubation Park construction project is an important support for the county to build nests to attract phoenixes and attract investment, and it is also a key project for advancing the "strengthening industry" action. The project is planned as a whole and constructed in phases. Phase I covers an area of 40 mu and builds 6 standardized factory buildings totaling 15,000 square meters. At present, the main steel structure installation of the 6 factory buildings has been completed, and they are expected to be completed and put into use in October.

Rebar tying, concrete pouring, equipment hoisting... At the construction site of the Zhuanglang County Runxiang Commercial Center construction project, accompanied by the roar of tower cranes, excavators, and various mechanical equipment, workers are racing against time and carrying out operations busy and orderly. The project has a total investment of 180 million yuan and covers an area of 30 mu. It will build a commercial center integrating a hotel, commercial complex, children's amusement park, warehouse, and parking lot.

The Zhuanglang County Cold Chain Logistics Industrial Park infrastructure construction project is built in two phases. The first phase of the project has completed the comprehensive service building and some ancillary facilities. The second phase of the project has completed the "three connections and one leveling" work and is currently undergoing bidding.

The Zhuanglang County Domestic Waste Incineration Power Generation Project is invested and constructed by Anhui Haichuang Green Energy Environmental Protection Group Co., Ltd. It focuses on solving the domestic waste problem of "three counties and one city"—Zhuanglang, Jingning, Huating, and Zhangchuan—incinerating 146,000 tons of domestic waste annually, with an average daily volume of 400 tons. At present, all works have been fully completed and will be put into operation in October.

The dry-mixed mortar and sand production line construction project of Zhuanglang County Shunsui Commercial Concrete Co., Ltd. will build one machine-made sand production line with an annual output of 600,000 tons, one dry-mixed mortar production line with an annual output of 300,000 tons, and one water-stabilized mixing station, as well as 21,400 square meters of production workshops, raw material warehouses, finished product warehouses, and business buildings. At present, equipment commissioning and the construction of raw material storage warehouse works are underway, and the main structure decoration work of the business building project is in progress.

The Zhuanglang County 30,000-head beef cattle slaughtering and processing production line construction project is a key project in the construction of Zhuanglang County's Pingliang Red Cattle industrial chain. The project is invested and constructed by Shandong Zhuangduoduo Food Co., Ltd. The project is built in two phases, of which Phase I involves an investment of 90 million yuan to build a 30,000-head beef cattle slaughtering line. At present, the main works such as the waiting-for-slaughter area, slaughtering area, cold storage and preservation area, power center, business building, quarantine room, waste harmless treatment point, and sewage treatment have been completed. In the near future, facilities and equipment for slaughtering, cutting, cold storage, and preservation will be purchased and installed, and the project is expected to be fully completed and put into use by the end of October.

Zhuanglang Xueyuan Agricultural Products Supply Chain Co., Ltd. was established in 2022 and is an apple supply chain enterprise integrating procurement, storage, primary processing, and market sales. The company is organizing and implementing the Phase II project, with an estimated total investment of 30 million yuan, to build a 6,003-square-meter steel-frame controlled-atmosphere warehouse and complete 6,000 square meters of courtyard hardening.

In order to achieve "acceleration" in project construction, Zhuanglang County has set up a major project breakthrough task force, implementing one enterprise, one policy, and full-process tracking services. In the project planning stage, it intervenes in advance to carry out preliminary consultation and guidance, project layout optimization, etc.; during project advancement, it regularly holds task force meetings to analyze and study the difficult and blocking issues in project advancement, propose solutions, and form an investment and business environment with the simplest approval, fastest processing, and best service, truly achieving "all-round" service, "all-factor" supply, and "full-cycle" tracking.

In the future, Zhuanglang County will, with rock-solid determination, grasp projects and develop industries, continue to take key project construction as an effective lever for stabilizing growth, accelerate the pace of transformation and upgrading, continuously improve the quality and efficiency of industrial development, treat the construction site as a battlefield and the scene as an examination room, and go all out to achieve "acceleration" in project construction on the new journey and new track of promoting high-quality development, continuously writing magnificent chapters of forging ahead on a new journey and making achievements in a new era.