In July 2024, the Snowy 2.0 construction team fractured the surrounding rock through high-pressure hydraulic blasting, allowing the Florence TBM to resume excavation. Previously, while constructing the Snowy 2.0 water conveyance tunnel, the Florence TBM experienced a prolonged shutdown because high-hardness, highly abrasive rock wore down the cutterhead's peripheral cutters.

The Snowy 2.0 project is Australia's largest renewable energy project. It will connect two reservoirs through 27 km of tunnels and a power station with pumping capability, enabling water to be released for power generation during peak demand and pumped back to the upper storage when there is surplus energy in the system, ready for generating power again.
Contract awarded for Oslo highway tunnel upgrade project in Norway
下一篇Jinan Metro Line 4 "Jinan University" Section Achieves Dual-Line Breakthrough

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)