46 Continuing Construction Projects in Chongqing Economic and Technological Development Zone Race Against Time to Advance Progress

2024-07-04 2439 0人评论

Recently, accompanied by the roar of machinery, at the construction site of the Tongluoshan Tunnel on Chongqing Rail Transit Line 27, construction workers were sweating profusely and pressing ahead with construction. That day, it was learned at the site that the overall excavation of the tunnel is now more than halfway complete, and it is planned to enter main-line tunnel construction in the fourth quarter of 2024.
  At the same time, it was learned from the Chongqing Economic and Technological Development Zone that in the first half of this year, 46 continued projects in the zone completed an investment of 4.989 billion yuan.
  Among them, projects such as the Chongqing East Railway Station railway hub, the eastern section of Hengshi Road, and the Guangfu Avenue project in B Standard Sub-zone of Chayuan New Area completed more than 50% of their annual planned investment progress, while projects such as Section 2 of the middle section of Zongsan Road, the road project on the south side of the Elegant Changle Residence plot, and the Guangyang Avenue ecological restoration and landscape improvement project exceeded 90% in overall image progress.
  Specifically, the Chahui Avenue (Section 1) project has fully entered the construction stage of the upper bridge structure, with 76% of the overall engineering volume completed, and is planned to achieve breakthrough by the end of 2024; construction of the Chongqing East Railway Station section of Rail Transit Line 6 is stepping up efforts to meet the schedule, and the main structures of stations such as Liujiaping Station, Baile Yuan Station, and Changsheng Laojie Station have all been capped; on the right line of the section from Kuangjiatang Station to Zhuyuancun Station of Phase I of Metro Line 24, the composite TBM was successfully launched, marking a further step forward in shield tunneling construction for this section.
  Transportation projects are advancing steadily, and industrial projects in the Chongqing Economic and Technological Development Zone are also racing against time to make progress.
  For example, the overall image progress of the Donggang Automotive Electronics Industrial Park project in the Chongqing Economic and Technological Development Zone has reached 90%. It is understood that the project will build warehousing and logistics buildings and supporting facilities, with a total planned gross floor area of 56,706 square meters, focusing on introducing high-value-added and high-tech intelligent new energy vehicle supporting enterprises to create a green, low-carbon, smart new complex.
  In addition, China Mobile Chengdu-Chongqing (Chongqing) Jiangnan Data Center (Phase I) is carrying out construction of internal and external curtain walls, outdoor pipe networks, and other works; the main structure has been completed, and image progress accounts for 70% of the total engineering volume, with completion and operation expected before August 2025. According to the plan, during the 14th Five-Year Plan period, the project can provide more than 6,600 racks and form at least 128P of computing power, meeting the needs of "East Data, West Computing" operations with high quality.