Pile Foundations for the Main Tower Pier of the Central Channel Bridge of the Hangzhou Bay Cross-Sea Railway Bridge All Completed

2024-06-18 1974 0人评论

6670d76051562.jpg

At 23:29 on June 16, with the pouring of the last truckload of concrete, the pile foundations of the **main tower pier of the central navigation channel bridge of the Hangzhou Bay Cross-Sea Railway Bridge were all completed. The project is managed and constructed by the Shanghai-Hangzhou Passenger Dedicated Line Company, designed by China Railway Major Bridge Engineering Group Co., Ltd. (MBEC) and China Railway Design Corporation, and constructed by MBEC.

The 160-meter-class deep bored piles of the central navigation channel bridge of the Hangzhou Bay Cross-Sea Railway Bridge are the deepest bridge bored piles in the world. The geological conditions at the bridge site are extremely complex: not only are there deep, collapse-prone sand layers and silt layers, but hard tuff is also distributed at the pile tips. Although the drill pipe diameter reaches 63 cm, when its length exceeds 150 meters it is like a long, thin "fishing rod," making it extremely difficult to maintain the hole shape and diameter and to drill into the rock layer at the bottom; once control is improper, there is also the huge risk of hole collapse and drill burial. The full completion of the pile foundations of the **main tower pier of the central navigation channel bridge marks substantive progress in the bridge's construction.

6670d7729fd6c.jpg

It is reported that the completed No. 81 main tower pier has a designed pile diameter of 2.5 meters, a pile length of 129 meters, and a hole depth of 154.5 meters. The bearing stratum at the pile tip is slightly weathered tuff, with a maximum rock-socketed depth of 14.24 meters. There are a total of 52 friction bored piles arranged in a plum-blossom pattern, and the designed concrete grade is C40 underwater concrete.

Due to the vast sea area of Hangzhou Bay, strong tides and rapid currents, strong scouring and silting, typhoon disturbances, and other harsh natural conditions, construction organization is extremely difficult and the construction schedule is exceptionally tight. The central navigation channel bridge is constructed entirely at sea; all engineering materials, mechanical equipment, and construction personnel must be organized through marine transport, and the complex marine environment further increases the difficulty of construction organization. In addition, hole formation and pile formation control for the 2.5-meter large-diameter ultra-deep bored piles are also quite difficult.

6670d7808f49b.jpg

During construction, the project team continuously summarized and explored, and proactively communicated with the client's project department to optimize construction techniques. They adopted the hole-forming processes of "800-type rotary drilling + 4000-type rotary drilling" and "800-type rotary drilling + 580-type (520-type) rotary drilling," fully leveraging the performance advantages of the 800-type rotary drilling rig. This increased drilling efficiency to 65-80 hours per hole, greatly shortening the hole-forming cycle and laying a solid foundation for the safe and rapid completion of the bored piles at Pier No. 81.

By continuously adjusting the mud mix ratio, innovating temporary construction structures, and optimizing resource allocation, construction efficiency was significantly improved, gradually rising from 3 days per pile at the beginning to 1 day per pile, with an average efficiency of 1.73 days per pile. The No. 81 main tower pier began drilling on March 18, 2024; after 90 days, the pouring of the last pile foundation was completed on June 16, 20 days ahead of the planned schedule. The pile foundation construction was successfully completed before the typhoon season arrived, seizing the initiative for the subsequent organization of cofferdam construction.

6670d7984da92.jpg

Project link

The Nantong-to-Ningbo High-Speed Railway is an important component of the coastal corridor of China's "Eight Vertical and Eight Horizontal" high-speed railway network. It starts from Nantong West Station on the Yancheng-to-Nantong High-Speed Railway, runs south through Suzhou City in Jiangsu Province and Jiaxing City and Ningbo City in Zhejiang Province, and leads into Ningbo Station in the Ningbo hub. After completion, the project will connect with multiple lines including the already operational Yancheng-to-Nantong High-Speed Railway, Beijing-Shanghai High-Speed Railway, Shanghai-Kunming High-Speed Railway, and Ningbo-Taizhou-Wenzhou High-Speed Railway, as well as multiple lines under construction such as the Jinhua-to-Ningbo Railway and the Shanghai-Nanjing Riverside High-Speed Railway. It will help make the road network structure of the Yangtze River Delta region more complete, greatly facilitate travel for people along the line, and be of great significance for promoting high-quality integrated development of the Yangtze River Delta.