Located within the former Donghu Building plot on the southwest side of the intersection of Daminghu Road and Heihuquan North Road. As an important station in metro construction, its construction quality and efficiency directly affect the completion and operation of the entire metro line.

Project difficulties
Due to the tight schedule, small site, and high difficulty, the project department ultimately decided after study to adopt the "rotary drilling, grab, and milling" construction process, which can greatly improve the efficiency of diaphragm wall formation.
Project overview
The diaphragm wall is designed with a thickness of 1 m and a depth of 34 m, totaling 81 panels. The uniaxial compressive strength of the rock in the hardest stratum is 80 MPa.
A total of 6 pieces of equipment from Shanghai Jintai participated in the construction of this project, including 5 trenching machines and 1 rotary drilling rig.
Facts have proven that no matter how complex or difficult the project, Shanghai Jintai will go all out and live up to our customers' recognition of us.
International Foundation Engineering Exchange: Opportunities for Chinese Enterprises Undertaking Foundation Construction Projects in Thailand!
下一篇Zhejiang University Once Again Confirms: Screw-Lock Connectors' Load-Bearing Capacity Leads International Levels!

2026-09-28 1137 0

2026-09-24 10491 0

2026-09-23 10629 0

2026-09-22 10708 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)