6月3日,中铁二局城通公司青岛地铁5-2-8标青医东院站-石老人浴场站区间右线顺利通过百环验收。
该区间段地层隧洞围岩破碎、稳定性差,存在大块岩体坍塌、卡机及涌水等风险。针对该构造破碎带,项目精心编制地面注浆专项施工方案,并严格按照方案要求,采用地面后退式注浆措施对该构造破碎带进行预处理,确保了TBM顺利掘进通过。过程中,项目管理人员与班组高度融合,不断革新班组“小发明”、“小创造”,尤其是班组提出的“管片三环拉结装置”,迅速扭转了始发段隧道管片错台较大的不利局面,推动后续成型隧道质量持续提升,管片无破损,且错台量最大值控制在5mm左右,为通过“百环验收”奠定了坚实基础。