The reporter learned from China Railway Shanghai Group Co., Ltd. that the Suzhou East Tunnel, a controlling project of the Nantong-Ningbo High-Speed Railway constructed by China Railway 14th Bureau Group, officially began shield tunneling on the 18th, marking important progress in the construction of China's longest urban high-speed railway tunnel.
The Suzhou East Tunnel on the Nantong-Suzhou-Jiaxing-Ningbo High-Speed Railway, designed for a speed of 350 kilometers per hour, has a total length of 15.57 kilometers and features a single-tube double-track configuration. It is currently China's urban high-speed railway tunnel with the highest construction standards and the longest mileage, and is known as the "China Urban High-Speed Railway ** Tunnel."

According to the introduction, the tunnel is adjacent to Yangcheng Lake and has a rich groundwater system. It passes beneath 3 railways, 2 metro lines, 4 rivers and lakes, more than 20 important municipal roads, and multiple structures, with a maximum burial depth of 58 meters and a maximum water and soil pressure exceeding 8 bar. The construction team and the construction management unit, Shanghai-Hangzhou Passenger Dedicated Line Co., Ltd., tailored the domestically produced super-large-diameter slurry balance shield machine "Tongyong Yuanmeng" (Nantong-Ningbo Dream), which is one of the most intelligent shield machines in China at present. It has an excavation diameter of 14.81 meters, a total length of 134 meters, a total weight of 4,200 tons, and a total installed power of 10,000 kilowatts. Targeted improvements were made in adaptability to ultra-long distances, pressure resistance, and corrosion resistance. It is equipped with advanced geological forecasting, automatic monitoring, and synchronous dual-liquid grouting systems, and applies multiple domestically leading core technologies such as an integral fully prefabricated box culvert and synchronous pushing and assembling.

The Nantong-Suzhou-Jiaxing-Ningbo High-Speed Railway is an important component of the coastal corridor of China's "Eight Vertical and Eight Horizontal" high-speed railway network. Once completed, it will connect with multiple lines including the already operational Yancheng-Nantong High-Speed Railway, Beijing-Shanghai High-Speed Railway, Shanghai-Nanjing Riverside High-Speed Railway, Shanghai-Kunming High-Speed Railway, and Ningbo-Taizhou-Wenzhou High-Speed Railway, further improving the layout of the road network structure in the Yangtze River Delta region and holding great significance for promoting high-quality integrated development of the Yangtze River Delta.
Total length 7,060 meters! Shengli Village Tunnel on the Xi'an-Yan'an High-Speed Railway successfully holed through
下一篇Suzhou East Tunnel Officially Begins Shield Tunneling

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)