After two and a half years of construction, the No. 2 inclined shaft to the exit section of the Binghui Tunnel, the second-longest tunnel on the Chongqing–Kunming High-Speed Railway, was successfully holed through recently. This major engineering breakthrough marks key progress in the construction of the Chongqing–Kunming High-Speed Railway and provides solid assurance for the completion and opening of the entire line.
The Binghui Tunnel, with a total length of 21.17 kilometers, is the second-longest tunnel on the entire line and a Class I high-risk tunnel, located within Yiliang County, Zhaotong City. The tunnel presents diverse risks, including seven types such as dangerous rockfall, collapse, sudden mud and water inrush, tunnel floor deformation, gas, large deformation, and rockburst, with 14 sections of extremely high risk and 30 sections of high risk.

The Binghui Tunnel is equipped with "2 cross adits + 2 inclined shafts + 1 parallel heading at the tunnel body," among which the No. 2 inclined shaft to the exit section is the **holing-through section of the tunnel. The holing-through section has a main tunnel length of 2,845 meters on the left line and 2,839.1 meters on the right line, with a total double-line main tunnel length of nearly 5.684 kilometers.

The Chongqing–Kunming High-Speed Railway is the ** high-speed railway with a design speed of 350 kilometers per hour within Yunnan Province, holding milestone significance in the history of railway development in Yunnan and opening up new space and bringing new opportunities for Yunnan's development.
Successful Breakthrough at the Exit and Cross Adit of Hujiayuan Tunnel on the Xi'an-Shiyan High-Speed Railway
下一篇No. 2 Inclined Shaft to Exit of Binghui Tunnel, the Second Longest Tunnel on the Chongqing-Kunming High-Speed Railway, Successfully Breaks Through

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)