On January 9, the double-line tunnel of Qingdao Metro Line 5, constructed by China Railway 14th Bureau Group, successfully passed beneath the Jiaozhou-Jinan Railway, overcoming a Level-1 risk source. This laid a solid foundation for the smooth operation of the Spring Festival travel rush and provided valuable experience for shield tunnel construction beneath operating railway lines.
As a major transportation artery in Shandong Province, the Jiaozhou-Jinan Railway handles more than 150 trains per day. After departing from Ruichang Road Station and advancing 17 meters, the shield machine entered the section beneath the Jiaozhou-Jinan Railway. The affected area of the dual-line shield crossing beneath the railway totals 270 meters in length. The undercrossing section lies in a fractured zone with poor rock stability, making construction extremely difficult.
To ensure the safety of railway operations, the construction team increased the density of monitoring points. During the undercrossing of the operating railway line, 24-hour automated monitoring was adopted, and tunneling parameters were optimized in real time based on monitoring data. At the same time, the construction team used simultaneous grouting and secondary in-tunnel grouting to replenish grout in a timely manner, ensuring overall stability of soil pressure and adding safety assurance for the railway line in the undercrossing section.

Ultimately, over the course of 39 days, the builders completed the undercrossing task with almost zero settlement and zero deformation, ensuring normal operation of the railway line.
Qingdao Metro Line 5 is a backbone rail transit line encircling the eastern coastal urban area of Qingdao. Once completed, it will greatly enhance the networked operation function of the metro system in the eastern central urban area, improve the urban traffic environment and travel conditions for residents along the line, and drive the planned development of Dagang, CRRC Science and Technology Park, Joyful Coastal City, and the Yanjiashan area.
Chengdu-Dazhou-Wanzhou High-Speed Railway Marks New Progress as "***" Bridge Reaches Key Construction Milestone
下一篇Domestically Produced Super-Large-Diameter Shield Tunneling Machine "Dinghai" Rolls Off the Line for Construction of the World's Longest and Largest-Diameter Undersea High-Speed Railway Tunnel

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)