Actively expanding investment is an important lever for stabilizing growth. At the start of the new year, construction of a batch of industrial projects is in full swing in Fujian, a major manufacturing province, getting the year off to a good start for stabilizing investment.
The new energy industry is an emerging competitive industry in Fujian. With machines roaring and material transport vehicles shuttling back and forth... Arriving at the construction site of the lithium battery smart manufacturing supporting industrial park project in Dongqiao Development Zone, Ningde, one finds a bustling construction scene pulsing with development vitality.
According to reports, the Ningde Dongqiao lithium battery smart manufacturing supporting industrial park project involves a total investment of 2.67 billion yuan and will powerfully advance the local improvement of supporting facilities for the lithium battery new energy industry, driving the industry to fill gaps, strengthen and extend its chain.
Led by leading enterprises, the industry clusters its chain. In recent years, relying on leading enterprises such as Ningde Times New Energy Technology Co., Ltd., Ningde City has attracted more than 80 industrial chain projects through investment promotion.
Putting on cleanroom suits, masks and gloves, then completing 10 seconds of dust removal in the air shower, workers enter the cell production workshop, where an important process in lithium battery production will be completed.
This factory is the lithium-ion battery production base of Ningde Times New Energy Technology Co., Ltd. in Fuding City. Chen Juntong, project preparation manager of the Fuding production base, said the entire base is planned overall with 5 cell factories and a planned capacity of 120 gigawatt-hours (GWh). At present, cell factories No. 1 to 4 have all been put into production, and factory No. 5 is preparing to start construction; once all are in production, they will achieve an output value of 100 billion yuan.
"The implementation and construction of this project will effectively promote the development of the local lithium battery new energy industrial chain," said Chen Xiaoping, deputy director of the Ningde Municipal Bureau of Industry and Information Technology. Since the project was launched, the local government has made every effort to provide service guarantees and pushed the project to achieve "accelerated speed."
Recently, the 8.6th-generation new display panel production line project of Xiamen Tianma Optoelectronics Co., Ltd., located in the Xiamen Torch High-tech Zone, achieved the smooth move-in of core equipment, marking a key step by the project toward the mass production goal.
"The equipment moved in this time is the core equipment, the exposure machine," said Hou Dongquan, general manager of Xiamen Tianma Optoelectronics Co., Ltd. After the exposure machine is assembled and debugged, the team will verify the equipment and process flow, as well as conduct small-batch trial production, laying a solid foundation for the project's mass production on schedule.
According to reports, the project involves a total investment of 33 billion yuan and mainly targets three application markets: automotive display, IT display and industrial product display. After the project is put into production, it will drive the upgrading of the local electronic information industry.
This is just one of the leading projects that have recently settled in the Xiamen Torch High-tech Zone. With the settlement of a batch of leading projects such as CALB, Inspur and Shenzhou Kuntai, related upstream and downstream supporting enterprises are accelerating their clustering, and the driving role of key projects in the Xiamen Torch High-tech Zone is increasingly evident.
Project implementation adds confidence, and investment growth stabilizes confidence. A relevant person in charge of the Fujian Provincial Development and Reform Commission said that at present, Fujian Province is continuously increasing project coordination efforts and persistently promoting project construction, forming good support for stabilizing investment.
Key Engineering Projects Under Steady Construction in Many Regions
下一篇Subei Makes Every Effort to Advance Key Projects and Achieve Phased Results

2026-09-28 1157 0

2026-09-24 10586 0

2026-09-23 10714 0

2026-09-22 10808 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project