G1503 Highway and Zhoudeng Expressway Pudong Hub Section Project
First diaphragm wall of Main Works Section 1
successfully completed pouring

The main works section 1 of the G1503 Highway and Zhoudeng Expressway Pudong Hub Section Project comprises a total of 266 diaphragm walls, with a thickness of 0.8–1.0 m, all adopting the GXJ joint type.
Project Overview

The project is located west of the planned Shanghai East Railway Station and is an important component of the "three vertical and five horizontal" rapid distribution system of the Pudong Hub. It will serve as the main external transport corridor of the Pudong Hub, improve internal connectivity and external links among the clusters along the route, and create conditions for high-quality integrated station-city development in the region. It is the inaugural project for building the Pudong Hub into a fully functional, world-class modern large-scale comprehensive transport hub.
Construction Difficulties
A 3.1 m thick sandy silty clay layer with abundant phreatic water exists in the shallow strata

1) Determine the collapse and necking conditions of each soil layer through trial trenching;
2) Adjust mud parameters and optimize the mix ratio based on the trial trenching results to reduce construction risks;
3) Improve trenching accuracy, reduce the impact of repeated correction on the trench section, shorten exposure time, and ensure trench stability;
4) Adopt pre-dewatering measures for the diaphragm wall.
Large project volume and tight schedule

1) Make full use of site conditions to carry out construction at multiple work faces;
2) Reasonably arrange the construction workflow and adjust it promptly according to site progress;
3) Increase investment in equipment and human resources to effectively improve construction efficiency.

Building Municipal Engineering Together! XCMG Trenchless Machinery Draws Attention and Investment in the Greater Bay Area
下一篇Opening Up New Markets in the Middle East and Creating New Development Opportunities | Tysim Machinery Makes Its Debut at the 2023 Iran International Construction Machinery Exhibition

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)