8月29日凌晨6时50分,历经10小时30分钟的连续施工作业,茶常高速控制性工程——耒水特大桥5#主墩左幅承台顺利浇筑完成。
至此,耒水特大桥6#、5#两座主墩承台混凝土浇筑全部完成,标志着大桥主墩全面转入墩身和0号块等上构施工阶段。
此次浇筑的耒水特大桥5#主墩左幅承台长15米、宽9.5米、高4.5米,采用C30混凝土浇筑,实际浇筑660方。为确保5#主墩承台混凝土顺利浇筑,项目团队科学组织施工,合理配置资源,严格控制各项工序,确保了左、右幅承台在8月下旬相继完成浇筑。
接下来,茶常高速将继续抢抓施工黄金期,围绕耒水特大桥总体施工计划,压实责任、凝心聚力,在保证安全和质量的前提下全力推进大桥各项上构施工作业。
2,502 Meters! Qinghoushan Tunnel on Panxing Railway Successfully Breaks Through
下一篇China's First: 29,000-Ton Double-Deck Bridge Completes Single Rotation, Guanfan Expressway Overpasses Guangzhou-Shenzhen Railway

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)