Bidding Announcement for EPC of Lengquan-Suoyu Highway Project on Gaozhen Line of Township Road
I. Industry: Highway
II. Tenderee: Gujiao Hongchang Transportation Construction Management Co., Ltd.
III. Project Overview:
The starting point is located in the south of Lengquan Village, Tunlan Street, connecting to the Tuncun-Taike Line Highway; the end point is at Suoyu, connecting with National Highway 241, the relocation project of the Fenhe Reservoir section of Provincial Highway Lanma Line, and the under-construction "Taiyuan Northwest Second Ring Expressway Haojiagou Interchange Connecting Line". Intermediate control points include Fengpingling, Yongshuqu, and Huili. The route length is 6.48 km. The highway technical standard adopts the third-class highway technical standard, with a design speed of 30 km/h, a subgrade width of 7.5 m, and a design vehicle load of Highway-II level. Main quantities: subgrade excavation 18,600 m3, subgrade filling 78,300 m3; drainage works 3,450 m3; subgrade protection and reinforcement works 52,376 m3 (rubble concrete protection); asphalt concrete pavement 43,890 ㎡; 3 bridges totaling 542 m; 18 culverts; traffic engineering and roadside facilities, etc.
IV. Planned Duration: The total planned duration is 545 calendar days, including 30 calendar days for the construction drawing design phase and 515 calendar days for construction. Defect liability period: 24 months from the date of actual completion acceptance.
V. Obtaining Bidding Documents:
Bidders intending to participate must register in the "Transaction Market Entity Database" column of the National Public Resource Trading Platform (Shanxi Province) (website: http://prec.sxzwfw.gov.cn/). For details, please refer to the Transaction Market Entity Database Registration Guide (website: http://jyzt.sxzwfw.gov.cn/ztxxzc/index.jhtml)。
Announcement Date: January 12, 2023
Deadline for Submission: 2023-3-14 09:30
Source: National Public Resource Trading Platform
Link: http://prec.sxzwfw.gov.cn/jyxxgczb/658390.jhtml
Bidding Announcement for Design and Construction General Contracting Project of New Campus of Hong'an County People's Hospital
I. Industry: Housing Construction
II. Tenderee: Hong'an County Urban Development Investment Group Co., Ltd.
III. Total Investment: 1,123.2163 million RMB
IV. Project Overview:
The planned total land area of the Design and Construction General Contracting Project of the New Campus of Hong'an County People's Hospital is 163,519 ㎡, and the total construction area of Phase II is 168,633.55 ㎡. The main construction includes one 4-story outpatient and emergency medical technology complex building with a construction area of 118,583.55 ㎡ (including a basement parking garage and civil air defense area of 36,500 ㎡), one 13-story inpatient building No.1 with a construction area of 25,880 ㎡, one 6-story inpatient building No.2 with a construction area of 12,120 ㎡, a logistics complex building with a construction area of 9,800 ㎡, a connecting corridor of 1,500 ㎡, an oxygen generation station of 150 ㎡, a sewage treatment station of 600 ㎡, and other supporting infrastructure such as outdoor works.
V. Planned Duration: 900 calendar days, planned start date: 2023-02-15
VI. Obtaining Bidding Documents:
All bidders intending to participate (if bidding as a consortium, all members of the consortium) shall register on the Hubei Provincial Electronic Bidding and Tendering Trading Platform (hereinafter referred to as the "Electronic Trading Platform", the same below) (website: www.hbbidcloud.cn)进行注册登记,并下载手机版CA(标证通)或办理CA数字证书(具体操作参见“电子交易平台”—办事指南—交易主体注册登记指南)。完成注册登记后,请于2023年01月13日至2023年01月17日24:00时止(北京时间、下同),通过互联网使用手机版CA(标证通)或办理CA数字证书登录“电子交易平台”,在所投标段免费下载招标文件。
Announcement Date: January 12, 2023
Deadline for Submission: February 7, 2023, 09:30
Source: Hubei Provincial Electronic Bidding and Tendering Public Service Platform
Link: http://www.hbbidcloud.cn/hubei/jyxx/004002/004002001/20230112/3648d8c8-90b1-451b-836b-e20fdede8a8b.html
Changzhou Yuchai Holds 2023 Business Work Conference and Advanced Commendation Meeting
下一篇Vice Mayor Peng Tao Supervises Sunward's Safety Production Work and Conducts New Year Visits

2024-10-08 13423 0

2024-09-30 13142 0

2024-09-20 12919 0

2024-09-13 13091 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)