6月14日,历经635天的紧张施工,随着最后一声爆破巨响,呼北国家高速公路山西段朔城至神池段控制性工程柴家墕隧道顺利贯通,为朔神高速公路按时全线贯通打下坚实基础。
柴家墕隧道由中铁二十二局承建,左洞长1898米,右洞长1870米,地质条件复杂,被设计院认定为近年来我省围岩条件最差的隧道。
自2020年9月12日开工建设以来,历经635天的辛勤奋战,建设者克服了溶洞发育、岩体破碎、湿陷黄土浅埋偏压、拱顶坍塌下沉等问题、难点,严格执行“管超前、短进尺、弱爆破、强支护、快封闭、勤量测”的原则推进隧道掘进。柴家墕隧道的贯通,是项目进程的重大节点,将朔神高速建设推向了新起点、新征程,为年度全线建成通车奠定了坚实的基础。
First Single-Head Excavated Tunnel on the Chongqing-Hunan Expressway Expansion Project Successfully Breaks Through
下一篇Baiyan Tunnel on Yixing Railway Successfully Breaks Through; All Tunnels Expected to Be Completed Within This Year

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)