11月15日上午,杭绍甬高速南阳隧道H基坑土方正式开挖。


H基坑作为南阳隧道第五个开挖的基坑,基坑长172m,宽36m,开挖深度12m,土方开挖量约7.6万方,该基坑涉地铁保护区施工,地铁盾构区间允许变形仅3mm,接下来将严格以地铁自动化监测数据指导施工。
杭绍甬一分部充分抓住施工黄金季,整合优势资源,集中力量,合理安排人力和机械等资源,为确保今年年底前实现既定目标,也为后续主体结构施工提供了更加坚实的质量与工期保障。