10月27日19时,历经36个小时的持续施工,温州轨道交通S2线SG3标盐盆站四线五连跨连续梁完成浇筑,比计划工期提前半个月完成任务目标。
S2线SG3标盐盆站出口处 (5×30)米四线五连跨连续梁,设计混凝土方量2950立方,采用等截面单箱四室混凝土结构。
为确保此次四线连续梁成功浇筑,市铁投集团建设分公司会同项目部多次研究优化桥梁施工方案和安全技术重点,对一线作业人员开展多次安全技术培训和施工技术交底,并在大体积混凝土浇筑前对各项准备工作进行细致的安排布置和严格的全面检查,确保建设工作万无一失。