On July 24, the left tube of the Kalu Moqi Tunnel on the S10 Zhuohe Expressway was successfully holed through, marking the completion of excavation for the first long tunnel of the Zhuohe Expressway project.
Gou Jiangwen: As one of the control works of the Zhuohe Expressway, the Kalu Moqi Tunnel has a total length of 3,950 meters, of which the left tube is 2,195 meters long. Since construction began in November 2019, all participating units have fought hard for more than 620 days and nights, ultimately achieving the milestone victory of the left tube breaking through first with high standards and high quality.
The Kalu Moqi Tunnel is located in Gensha Village, Wanmao Town, Zhuoni County, at an average altitude of 3,190 meters. The tunnel site lies in the cold and humid region of Gannan, and the surrounding rock is mainly Grade IV and V. During tunnel construction, water inflow, collapse, rockfall and significant sudden changes in surrounding rock occurred repeatedly, and the surrounding rock was extremely unstable. Since the start of the project, all construction personnel have overcome many unfavorable factors such as high altitude, tight schedule, heavy tasks and complex geological conditions, and have ensured the smooth breakthrough of the tunnel through forward command, scientific organization and refined construction.
Qi Liangbin, Chief Engineer of the Zhuohe No. 8 Bid Section Project: Since the start of construction, Gansu Road & Bridge has always adhered to the management philosophy of high standards and strict requirements, strictly controlling quality and safety, and racing against time. Faced with the plateau climate and various difficulties, all project personnel have persevered. In response to repeated water inflow, collapse, rockfall and significant sudden changes in surrounding rock during tunnel construction, timely measures were taken to effectively ensure tunnel construction safety, demonstrating with practical actions the sense of responsibility of road and bridge builders.

As a landmark project of Gannan Prefecture's goal of "expressways reaching every county," the Zhuohe Expressway is of extremely great strategic significance for completely breaking the traditional transportation pattern of the three counties and cities along the route, promoting the building of a major transportation artery and economic corridor, advancing the opening-up, development and prosperity of the areas along the route and even the whole prefecture, comprehensively building a regional, networked and systematic all-for-one tourism expressway corridor, promoting the development and sharing of distinctive advantageous resources, and accelerating the pace of the rural revitalization strategy.
Li Yongpeng, Chief Engineer of the Zhuohe Expressway Construction Project Management Office: Next, focusing on the overall project arrangements, we will continue to strengthen construction management, strictly enforce project supervision, quality supervision and construction environmental protection, and build a first-class project with first-class management, first-class quality and first-class performance. We will strive to build the Zhuohe Expressway into an eco-friendly road, a premium tourism road and a road of prosperity for the people, and make new contributions to building a modern comprehensive transportation system and accelerating the construction of a happy and beautiful new Gannan.
Badong Tunnel, the Last 10,000-Meter-Long Tunnel on the Zhengzhou-Wanzhou High-Speed Railway, Is Completed
下一篇Zheibai Tunnel on Luoba Expressway Fully Breaks Through

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)