7月18日,三明莆炎高速沙溪大桥主桥首节段钢桁梁吊装成功,标志着大桥建设正式迈入主桥钢桁梁施工的快车道,为沙溪大桥早日实现贯通打下了坚实基础。
沙溪大桥主桥上部结构主跨采用100 米+176米+176米+100米的钢桁组合连续钢构(分84个节段)。主桥钢桁梁采用缆索吊机进行安装,额定起重量为130吨,钢桁梁节段最大吊重为103吨。此次吊装的钢桁梁节段重达97吨,安装在主桥6号墩约95米高的预定位置。
为确保此次钢桁梁吊装的顺利完成,项目部提前组织召开方案专家评审会议,开展缆索吊静、动载试验,并对全体施工人员开展安全技术交底,确定最优方案,明确人员分工。现场吊装时,在做好各项安全应急举措工作后,施工人员与吊装机械紧密配合,保证了整个吊装过程的安全、可控。
Jing'ao Line Intermediate Repair Project Expected to Be Completed by End of July
下一篇Main structure of WulingTou Tunnel on Wuhu-Huangshan Expressway completed; substructure of Qingyi River Grand Bridge fully finished

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)