Henan Province Further Advances Key Municipal Projects

2021-07-07 1055 0人评论

Recently, Sanmenxia City in Henan Province held a work promotion meeting on key project construction and the "Four Comparisons and Four Checks" initiative, implementing the relevant spirit and requirements of provincial and municipal key project construction work, briefing and analyzing the progress of key project construction and the implementation of the "Four Comparisons and Four Checks" across the city, commending outstanding units, summarizing experience, clarifying responsibilities, refining objectives, and studying measures to further advance the city's key project construction work.

Fan Fuzhong, Member of the Standing Committee of the Sanmenxia Municipal Party Committee and Executive Vice Mayor, put forward specific requirements for the city's key project construction work. First, summarize achievements and clarify the orientation. It is necessary to systematically summarize the achievements made in key project construction, establish a clear work orientation of vigorously pursuing projects and pursuing them strongly, and place the planning and advancement of industrial projects in a prominent position in project construction work.

Second, identify problems and grasp the key points. It is necessary to deeply analyze the shortcomings and deficiencies constraining the development of key project construction in Sanmenxia City, and coordinate the advancement of various projects such as innovative research and development, industrial development, infrastructure, and livelihood security. All functional units must follow the requirements of the administrative approval system and the "streamlining administration, delegating power, improving services, and optimizing the business environment" reform, implement conditional acceptance processing, open green channels, optimize approval processes, improve service efficiency, and create a favorable environment for project construction.

Third, focus efforts precisely and achieve practical results. It is necessary to strengthen the concept of "projects as the priority," continuously enhance work initiative and creativity, closely follow industrial policies, center on Sanmenxia City's "335" industrial system, and, in light of existing advantageous leading industries, target the planning of a batch of projects with strong relevance and high technological content and added value.

Fourth, strictly enforce rewards and punishments and strengthen incentives. Establish reward platforms and supervision platforms, strengthen the reward and punishment mechanism for key projects, and promote the city's key project construction work to a new level. At all levels, units should take the commended advanced units as examples, pioneer and innovate, forge ahead with determination, strive to open up a new situation for the city's key project construction, and make new and greater contributions to building a strong provincial-level regional central city.


评论 (0)

TOP