近日,经过全体员工数日奋战,临连高速公路多项工程节点提前完成,为年底“保开通”目标迈出坚实一步。
临连高速公路项目主线长5.693千米,共设置4座桥梁,32根墩柱(含高墩12根)。6月9日,将军庙中桥桥台顺利浇筑完成,比计划工期提前7天;沙归大桥圆柱墩顺利完成浇筑,比计划工期提前6天;K5+200-K5+490段路基完成填筑,具备交工验收条件,比计划工期提前2天。
一分部署,九分落实。临连高速项目调整资源配置、细化工期任务、严肃考核问责,按照“奋战在临连、立功在临连、创誉在临连”的工作理念,克服混凝土运距长、材料供应短缺和工期紧张等困难,抢抓黄金施工期,全面提高标准化施工水平,致力于打造样板工程、平安工地,向建党100周年献礼!
Fuzhou's First Road-Rail Dual-Purpose Bridge: Daoqingzhou Bridge Cross-River Section Completed, Setting China's Longest Span for Its Type
下一篇Feasibility Study Report for Yingjing-Leshan Expressway Project Passes Review, Construction to Begin in 2022

2026-09-28 1157 0

2026-09-24 10586 0

2026-09-23 10714 0

2026-09-22 10808 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)