Stratum Conditions
Location (Province): Shandong
Location (City): Jinan
Drilling Rig Model: MXL-150D2 Crawler-Type High-Lift Anchor Drilling Rig
Drilling Tool Configuration: 89 triple jet grouting drill pipe
Process Type: Jet grouting water stop
Construction Process: Triple jet grouting
Stratum Conditions: 1-2 m backfill soil, 3-16 m soil layer
Construction Angle (°): 90
Hole Diameter (mm): 700
Hole Depth (m): 16
Construction Efficiency (min): 120
Pure Drilling Time (min): 10
Pure Drilling Tool Removal Time (min): 10


Construction Process
Equipment: MXL-150D2 drilling rig, 89 triple jet grouting drill pipe and drill bit
Backend: 3E120C high-pressure grouting pump, ZB2-150 grouting pump, screw air compressor + 0.8 m³ air storage tank, cement mixing system
1. Level and organize the construction site;
2. Lay out pile positions according to the drawings;
3. Position the drilling rig at the pile position and adjust the angle to be vertical to the ground;
4. Prepare cement slurry and filter it twice into the slurry tank;
5. Drill the drill pipe to the required predetermined depth and carry out jet grouting operation; lifting speed 12-15 cm/min, rotation speed 12-15 r/min, water pressure 28-30 MPa, slurry pressure 1-2 MPa, air pressure 0.7 MPa;
6. When the drill bit is lifted to the hole opening, reduce the pressure of the high-pressure water pump;
7. Pull out the drill pipe, clean the grouting pump, drill pipe, grouting pipe, etc. with clean water, and move the machine to the next pile position for construction.
——Anman Drilling Rig After-Sales Service: Lu Xinke
Product Construction Introduction
Various Construction Applications of the MXL-150D2 Crawler-Type High-Lift Anchor Drilling Rig
01. High-lift construction in Mile, Yunnan

02. Auger drill pipe construction in Wuhan, Hubei

03. Soil nail wall construction in Xiyang, Shanxi

04. Grouting pilot hole construction in Liwan, Guangdong
05. Anti-floating anchor construction in Changsha, Hunan

At 5,100 Meters Above Sea Level, That Shining XCMG Gold
下一篇SANY Joins Forces with China Telecom and Huawei to Launch the Equipment Manufacturing Industry's First 5G Fully-Connected Factory

2025-10-11 12785 0

2025-10-11 12334 0

2025-10-11 12498 0

2025-09-11 12042 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)