5月29日,伴随着水泥泵车的轰鸣和最后一方混凝土的浇筑完成,深圳地铁13号线宝石路站正式吹响了主体结构封顶的号角,成为全线第9座主体结构封顶车站。
宝石路站呈南北向埋设于田心大道和如意路下,车站全长约293.6m,南接1125m的罗宝区间,北接584m的宝上区间,南北两端均设盾构始发井,是四工区唯一一座两端均始发的车站,也是四工区第三座主体结构封顶车站。
宝石路主体结构顺利封顶,标志着下一步项目将全面进入附属结构及内部结构施工阶段。
First Shield Machine Launched for Section 2 of the Joint Utility Tunnel along Shenzhen Rail Transit Line 14
下一篇Zhejiang Plans 245 Major Construction Projects with Total Investment of 8,263.7 Billion Yuan

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project