On May 17, with the successful demolition of the last overpass, the demolition and removal of all overpass bridges along the Yangmao Expressway expansion project was officially completed, marking another solid step toward the goal of completion and opening to traffic by the end of the year.
During the project construction period, a total of 28 overpasses needed to be demolished and newly built along the Yangmao Expressway. The smooth demolition of these 3 overpass bridges this time resolved the bottleneck in building eight lanes and will help facilitate the smooth implementation of the subsequent pavement works. This overpass demolition task spanned both Yangjiang and Maoming, with long distances between construction points, heavy traffic volumes along the construction points, and high difficulty in traffic organization, creating certain pressure to maintain smooth traffic flow.
To this end, the Yangmao Expressway expansion project coordinated with multiple parties including traffic police departments, expressway operators, and construction units, refined the traffic organization plan, adopted a fully closed diversion and control model of "expressway to expressway," set up warning signs level by level starting from distant points, and carried out work such as ensuring the passage of transport vehicles, traffic diversion, and clearing service areas, ensuring safe and orderly construction and traffic and improving construction efficiency.
At present, the Yangmao Expressway expansion project has completed 100% of its subgrade works, 90% of its bridge works, and 72% of its pavement works, and is expected to be completed and opened to traffic by the end of this year.
First Public Disclosure of Environmental Impact Assessment for the Ankang–Chongqing Section of the Newly Built Xi'an–Chongqing High-Speed Railway
下一篇Steel Girder Hoisting Completed for Lancang River Grand Bridge on Jinghong-Hai Highway

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)