4月6日,镇广高速王通段春在隧道左线贯通。至此,历时7个月,春在隧道顺利实现双幅贯通。该隧道全长1342米,是全线第二座双幅贯通隧道。
春在隧道地质构造复杂,施工难度大。自开工以来,四川铁投集团所属镇广高速公路公司落实规范化管理,精细安排资源保障要素,精准采取调控纠偏措施,在确保质量安全的前提下,按照预定工期实现春在隧道双福贯通。
截至目前,镇广高速王通段已相继贯通7座桥梁和3座隧道,其中双幅贯通隧道2座。主线路基土石方挖填基本成型,路面水稳已进入施工阶段。主线桥梁下部结构已完成80%,梁板预制已完成42.82%,架设已完成34.39%。隧道单洞进尺已完成83.55%。路面摊铺、房建施工、机电工程、交安工程等正稳步推进。
Xiamen Second West Channel (Haicang Tunnel) Project Completes Full-Length Secondary Lining
下一篇A "Graceful Turn" over the Beijing-Guangzhou Railway: Main Tower of China Railway Major Bridge Engineering Group's Rotational Cable-Stayed Bridge Capped

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)