近日,福州滨海快线项目部东门站首幅地下连续墙顺利开槽。
该站地下连续墙共47幅,计划分两期完成施工。本次施工的一期地连墙共计26幅,墙厚为1000毫米,深度为30.5-33.5米,墙底入中风化花岗岩及微风化花岗岩,入岩深度为2-9米,岩石强度平均值约为160兆帕。
该项目克服了主城区交通疏解难、施工区域场地狭小、交叉作业安全风险大,文明施工、环境保护要求高,年关将至加上疫情反弹导致劳动力匮乏等不利因素,超前谋划,组织人员对开工前各项准备工作逐项梳理落实,结合现场实际情况,不断优化施工方案,利用15天时间完成了开工前场地临建、方案评审、设备进场组装验收、人员培训等准备工作,确保了首幅地墙按期开槽。
该项目表示将合理利用现有资源加快施工进度,推进东门站一期围护结构施工,争取早日进入二期围挡施工。
All Continuous Beams of the Longest Bridge on the Fuzhou-Xiamen High-Speed Railway Successfully Closed
下一篇The Toughest "Hard Bone" of Nanchang Metro Line 4 Achieved Breakthrough

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)