近日,珠江三角洲水资源配置工程B3标“粤海37号”盾构机创下单班掘进10环(16米)、日掘进18环(28.8米)的新纪录。
“粤海37号”为开挖直径8.65米的泥水盾构机,盾构区间长度3196米,段洞身岩土体为弱风化泥质粉砂岩类,下穿狮子洋水道穿过多条断层破碎带,地质条件复杂。为了确保盾构机顺利、快速掘进,项目通过超前决策、优化施工方案、召开专家会议等举措攻克了分体始发场地面积不足、仓内积渣、盾构刀盘管理等难题,过程中不断总结提升,极大地提高了施工效率。
截至目前,“粤海37”号已掘进600米。下一步,项目将根据当地疫情防控政策提前筹划施工安排、合理调整资源配置,狠抓生产安全不放松、疫情防控不放松,持续保持稳产高产态势,开启项目工程建设新征程。
Jinan's Widest Yellow River Bridge Tops Out: Future Crossing in Under 4 Minutes
下一篇Fourth TBM 'Yuehai No. 25' Successfully Launched on Section A6 of the Pearl River Delta Water Resources Project

2026-10-18 0 0

2026-10-18 0 0

2026-10-17 0 0

2026-09-23 10598 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)