6月18日,水电四局小山口三级水电站厂房主体混凝土开始浇筑,此次浇筑部位为安装间下部集水井底板。
自厂房开挖至今,由于受到当地居民阻工、厂房基岩渗水、设计图纸严重滞后等影响因素,项目部及时联系业主解决阻工问题;敦促业主、设计单位尽快供图;千方百计控制厂房基岩渗水;内部优化资源配置,做好土方开挖施工向混凝土施工转轨工作,最终使得小山口三级水电站厂房主体混凝土顺利开盘浇筑。
目前,小山口三级水电站以厂房混凝土施工为主线,全面展开排冰道、前池空腔式挡墙、溢流堰等部位的混凝土施工。