Professional shotcrete reinforcement, foundation pit support reinforcement, mountain slope protection reinforcement, foundation reinforcement, anchor bolt and shotcrete reinforcement
A construction process that uses pressure machinery to spray concrete onto the surface of components to increase their cross-section. It includes construction procedures such as steel bar anchoring, soil nails, steel bar tying, and concrete spraying.
I. Scope of application:
1. Applicable to enlarging the cross-section of beams, slabs, columns, and walls to improve bearing capacity, repairing components after fire, and reinforcing brick walls in brick-concrete structures
2. Applicable to shotcrete slope protection for foundation pits 3. Applicable to shotcrete slope protection for mountains 4. Applicable to shotcrete slope protection for earth slopes
II. Shotcrete description
The strength grade of shotcrete for slope protection is C10-C50. This project adopts dry spraying technology, and the spraying machine model is PZ-5B. The dry spraying capacity of this machine is 5~5.5 m3/h, the conveying distance can reach 200 m horizontally and 40 m vertically, the motor power is 7.5 kW, and the air compressor working power supply is 380 V/75 kW. The rebound rate of concrete spraying is 25~35%.
Grade C10 raw materials for shotcrete. General material requirements: cement not lower than 425#, medium sand (moisture content controlled at 5%~7%), crushed stone particle size less than 15 mm, water source pressure 0.15~0.2 MPa, admixture (accelerator, dosage meeting design requirements). The construction mix proportion shall comply with the laboratory mix proportion requirements.