Over Half of Subgrade Works Completed on Longhai Section

2016-05-06 611 0人评论
        Recently, in Chongfu and Shangyuan villages, Bangshan Town, Longhai City, construction teams have been accelerating bridge construction on the Longhai section of the Xiamen-Zhangzhou Intercity Expressway. To date, a cumulative investment of 2.072 billion yuan has been completed for this section. Except for some sections still carrying out bridge substructure construction, all other contract sections have entered bridge superstructure construction, and soft subgrade treatment is also underway. Bridge works are 47% complete, and subgrade works are 52% complete.

 The Longhai section of the Xiamen-Zhangzhou Intercity Expressway starts at Dongmei Village, Zhangzhou Taiwanese Investment Zone, and ends at Changbian Village, Yancuo Town, with a total length of about 9.8 kilometers. Land acquisition and relocation for the project are the responsibility of Longhai City. Land acquisition has been completed, and house demolition has reached 245,000 square meters, accounting for 78%.  