记者在B5标段看到,施工区域一边是原老外环桥体,一边是通往雅山的大坡,另一边又是最近距离不到10厘米的居民住房。
据朱文明介绍,B5标段最难的就是宝山路-雅山大坡10个桩基的挖凿。一个桩基正常情况下3小时能旋挖完成,而目前靠人工挖凿1小时只能挖1厘米的深度,一天的进度最多20厘米。
为不影响施工进度,他们一个办法是采取用火烧岩石产生高温,再用稀释的醋瞬间冷却,然后进行人工挖凿;另一个办法就是用强酸浸泡,看是否能把岩石钙化后,再人工挖凿。