记者了解到,朝阳大桥为六塔七孔单索面斜拉桥,大桥跨越赣江范围全长约1560米,分为主桥和引桥两部分。6个主墩每个设有14根桩基,共计84根桩基,它们将担负起桥梁最重要的支撑作用。
经过111天的建设,主桥主墩桩基施工按计划在4月27日22时全部完成。4月28日,朝阳大桥西侧引桥部分第一根桩基开始施工,主桥主墩承台和东西引桥桩基的施工展开。目前朝阳大桥已有一个主墩钢围堰顺利水下着床,另一个主墩钢围堰已顺利起吊,其他4个主墩钢围堰正在加紧施工拼接中。