白石天河大桥全长826米,134根钻孔桩,78根墩柱,为单塔斜拉索桥。大桥主墩有20个钻孔桩,深达63米,均位于白石天河靠近北岸水中。
据介绍,白石天河地质状况复杂,有22米深泥沙岩、20米流动性极强的流溯、30多米深沙层等,这给钻孔打桩造成较大困难,“钻孔最困难时,一个钻机4天钻一米深,折断了4根反循环钻机钻杆”。为突破难题,项目部专门成立了科技攻关小组。他们反复研究论证,采用大功率反循环钻与冲击钻接力钻孔施工方法,最终攻克了易穿孔、缩径、地质不稳定等诸多难关,大大降低了施工成本,缩短了施工工期。截至目前,白石天河大桥已经完成90根桩基、20根墩柱、10个系梁和2个盖梁施工。