What Are the Main Construction Procedures of a Long Spiral Drill Rig?

2014-09-18 639 0人评论

  [Student Question] What are the main construction procedures of a long spiral drill rig?
  [Answer] Laying the cushion layer, setting out pile positions, positioning the drill rig, selecting materials, mixing materials, drilling, transporting silt away, feeding materials, lifting the drill, forming the pile, moving the drill rig, and testing the pile.
  From the perspectives of safety and quality, because the four procedures of mixing materials, drilling, feeding materials, and lifting the drill involve the quality of the mixture, the length of the pile body, the solid density of the pile body, and whether pile breakage will occur, they are key procedures; the rest are general procedures.
  The above content is compiled based on problems encountered by students in actual work, for reference only. If you have any questions, please communicate with us promptly for correction.