9时17分,1000吨和260吨履带吊车同时启动,直径2.05米,长81.9米,重174吨的乙烯精馏塔缓缓立起。9时28分,乙烯精馏塔完成整个“起立”动作,溜尾吊车顺利摘钩,主吊车涨杆,慢慢向基础移动。9时38分,1000吨履带吊车缓缓旋转,乙烯精馏塔稳稳地立在基础上。
本次大件吊装总共有13台塔类设备,十建临沂工程项目部经过合理的组织,精心的准备,克服了设备到货滞后,时间集中等困难,在短短半个月内将11台设备模块化吊装的准备工作完成(其中2台设备必须进行分段吊装,不具备模块化施工条件),劳动保护、附塔管线、防腐保温等全部安装完毕。