(2) Before the caisson is sunk, protective and environmental protection measures shall be formulated for the affected areas such as nearby levees and buildings in accordance with design requirements, and an observation system shall be established during the sinking process.
(3) The concrete of the first section of the caisson must reach the design strength, and each section above it must reach 70% of the design strength before sinking can begin.
(4) After the caisson is sunk to the design elevation, the geological conditions of the foundation base shall comply with design requirements. If the geological conditions of the foundation base do not conform to the design, it shall be promptly reported to the design unit for verification.
(5) The height from the cleaned foundation base to the bottom of the partition wall, the exposed height of the sloped surface of the cutting edge, and the effective area shall comply with design requirements.
(6) In soft soil, after the caisson reaches the design elevation and the foundation is cleaned, settlement observation shall be carried out, and bottom sealing may proceed only when the cumulative settlement within 8 hours is less than 10 mm.
(7) Water may be pumped and filling may be carried out only after the bottom-sealing concrete reaches the design strength. The filling shall comply with design requirements.
Cast-in-Place Reinforced Concrete Prestressed Box Girder: Foundation Treatment
下一篇文昌路西延工程新进展 上跨铁路西引桥桩基完工

2024-09-29 13335 0

2024-09-20 13336 0

2024-09-20 13180 0

2024-09-19 12457 0

Lize City Air Terminal Underground Main Structure Nearing Completion: Maximum Transfer Walk Under 4 Minutes After Operation

Anti-seepage Curtain for Main Lock Pit of CSCEC Port Shenqiu Double-Line Lock Project Completed on Schedule

All Pile Foundations Completed on Quanzhou Baiqi Channel

Hainan Upgrades Housing and Municipal Infrastructure

First Foundation Concrete Pour Successfully Completed for Zambia Kafue West–Muzuma 330kV Transmission Line EPC Project
Hot News
评论 (0)